Appendix C - timescales
All timescales relate to calendar days
|
Activity |
Timescale |
|
IRD to CPPM |
Within 28 days |
|
Planning the CPP meeting |
At least 5 days notice of meeting |
|
Pre-birth CPP meeting |
Within 28 days of CP initiation or within 28 weeks of gestation |
|
Completion of CP Assessment Report |
21 days from initiation of CP investigation |
|
Review CPP Meeting |
Within 6 months of CPPM |
|
Review of pre-birth CPP Meeting |
May be held within 3 months but requires professional judgement about most appropriate timing |
|
Summary of key decisions and agreed actions from CPPM |
Within 48 hrs |
|
Minute (note of meeting) CPPM |
Within 10 days |
|
Child protection plan |
Within 10 days |
|
Inquorate Meeting |
New meeting must be held within 10 working days |